ABOUT THIS PROJECT

Project completed August 30, 2023

The Campbell River Airport (YBL) is getting ready to welcome some much-needed rehabilitation and replacements to some of its heavily used infrastructure. The City has received financial support from Transport Canada’s Airport Capital Assistance Program (ACAP). YBL applied back in 2020 and was successful with Transport Canada contributing approximately $4.3 million towards Airport assets renewals with the City providing the remaining funding. 

The Campbell River airport requires upgrading and replacement of the runway lighting, visual aids and taxiway "B". The following list provides a general understanding of what these improvements are:    

 

  • Mill and overlay of the pavement along taxiway bravo
  • Crack sealing to reduce risk of FOD (foreign objects)
  • Mill and Pave existing asphalt to 100 mm and addition of new concrete aircraft stands for Apron 1
  • Replace Runway 12 SSLAR (solar lights)
  • Replace Runway 30 ODALS with SALS (directional lights)
  • Replace PAPI (runway approach path indicator lights)
  • Replace Airfield Signage
  • Replace Windsocks
  • Replace Beacon
  • Replace Apron Floodlights
  • Install Backup Wireless Communication for ALCS (lighting)
  • Install New Fire Suppression and Alarm in the FEC (field electrical centre)

FREQUENTLY ASKED QUESTIONS 

 

CR Airport (YBL) Lighting, Visul Aids and Taxiway Rehabilitation FAQs

  • What is the project?

  • Where is the project?

  • Who has been involved in developing the plans?

  • Who will be constructing the work?

  • When is the construction work going to take place?

  • What is the cost of the project?

  • How will traffic be managed during construction?

GETTING AROUND DURING CONSTRUCTION

All of the work is limited to the Campbell River Airport site so there is no disruption to traffic expected as part of this project and the City’s intentions are to minimize disruptions to the airport operations.

CURRENT TRAFFIC NOTIFICATIONS

No notifications at this time.

PROJECT PROGRESS

Project Milestones - Airport Reduced Visibility Lighting & Taxiway Upgrade

QUESTIONS?

For more information, contact the Capital Project Department at capital.projects@campbellriver.ca or 250-286-5756

Featured
What's New
Upcoming Events
Jun 01 - Sep 21, 2025 Farmers’ Market & Arts Faire
Oct 11 - 12, 2025 Campbell River Spirit Fair
Oct 24, 2025 Monster Mash!
Nov 20, 2025 National Child Day
Nov 27 - 28, 2025 Gingerbread House Competition
Nov 28 - 30, 2025 Deck The Downtown
Nov 29 - 30, 2025 Toy And Craft Show 2025
Dec 14, 2025 Breakfast With Santa