Campbellton Sewer System Upgrades

Details
Project Type
Utilities (water, sewer and drainage)
Project Status
Current

1749 19 Ave
Campbell River BC V9W 4M4
Canada

About this Project

During winter weather, the sanitary sewer system in the Campbellton catchment area experiences flows that exceed its design capacity. This project will upgrade key infrastructure to improve system performance and reduce the risk of overcapacity during wet weather.

Location and Timing 

This project will impact the sanitary Pump Station No. 2: 1749 19th Avenue related infrastructure: Highway 19A, between Tamarac Street and Petersen Road. It is currently in the design phase. Construction is anticipated to take place from fall 2026 through spring 2027, pending final approvals.

Project Team

The City has partnered with ISL Engineering  Services Ltd. to provide engineering, surveying, and project management services. A construction contractor has not yet been selected. A public tender will be issued once the project scope and budget are approved by Council.

Traffic Updates

All City of Campbell River Traffic and Service updates are shared at campbellriver.ca/government/news/traffic-updates.

Subscribe for City Traffic and Service Updates to receive the latest traffic notifications directly to your inbox at campbellriver.ca/subscribe.

Project Progress

  • Groundwater Sampling

    On March 17, 18 and 24, 2026, the City will be conducting ground water sampling within and around the project limits. 

  • Geotechnical Investigation

    From February 3 to February 20, 2026, the City will be conducting geotechnical investigations within and around the project limits. 

  • RFP-23-37 Awarded

    RFP-23-37 was awarded to ISL Engineering Services Ltd in July 2023

Questions?

For more information, contact the Capital Projects Department at capital.projects@campbellriver.ca or 250-286-5756.