The waterfront sewer main, built in 1972, is a critical piece of infrastructure that needs to be replaced to support new growth in the community and help protect the waterfront.
The new sewer pipe is now full installed. Work is underway on the construction of three new lift stations, scheduled to be complete by spring 2021.
This sewer work is part of the Waterfront Project 2018-2020. For updates about other construction making up that project in 2020, visit the Highway 19A Upgrades project webpage here.
Learn More
Getting Around During Construction
Work along the highway is now underway. Expect delays and intermittent single-lane alternating traffic. Closure notices will be posted here.
See the Alternate Routes Map
To sign up for email updates, please email capitalprojects@campbellriver.ca
Follow along with current project updates and milestones. more...