PROJECT PROGRESS DIARY

Keep up-to-date on progress, events and milestones related to the Rockland/Alder PRV Upgrade Project. Interested in receiving updates via email as they occur?
Email us at: alder.prv@campbellriver.ca
PROJECT MILESTONES
|
May 2012 |
Tender No. 694 cancelled due to insufficient funds. Project will be redesigned and retendered within 8 weeks. |
|
| Mar 2012 |
Tender No. 694 posted to City Website |
Tender No. 694 |
| Dec 2011 |
50% Design Complete |
|
| Sep 2011 |
Design Commenced |
|
| Jun 2011 |
Koers engaged under RFO 08-11 |
|
|
|
|
| |
|
|